Use this software handover acceptance checklist to decide which operating tasks a receiving team can accept for a stated system version. Pharos Production's custom software development services describe engineering delivery and written planning for major vendor dependencies. Use the pack to request the receiving evidence your engagement will include.
This is a reusable worksheet for a planned transition into operation. It contains a blank working database, field definitions and an explicitly fictional review. It records no completed customer handover or executed build, deployment or recovery exercise.
Before adding checks, agree the system, environment, source revision, deployed release and operating tasks being transferred. Name the receiving decision owner and the outgoing team's remaining duties. Record dependencies that stay with a cloud provider or another supplier. Repository ownership alone does not establish authority over those services.
Use one database row for one acceptance check against that boundary. Split a check when its tasks can reach different outcomes. For example, producing an artifact and restoring application attachments need separate criteria and evidence. Keep the agreed boundary with each row so a passing staging check cannot be mistaken for production acceptance.
Google SRE's engagement model describes service-specific readiness reviews before a team assumes production responsibility. The fields and decision rules here are an editorial template, not a prescribed Google standard.
Reproducible Builds defines reproducibility through bit-for-bit identical specified artifacts from the same source, environment and instructions. If that is a requirement, record the artifact comparison and its conditions. A second successful compilation without that comparison is only the narrower build check.
Duplicate this page into your workspace to edit the child database, Working Handover Checks. Start in a private copy before adding project information. The public original has zero assessment records; the fictional example below stays outside it.
Keep private evidence in approved storage and record a usable reference. Do not add secrets, customer records or private system identifiers to this public template. Leave unknown owners and dates blank while keeping the check Pending.
| Field | Type | What to record |
|---|---|---|
| Check | Title | One operating task or acceptance check |
| System and environment | Text | Included component, target environment and scope boundary |
| Artifact and version | Text | Source revision, release and relevant configuration references |
| Acceptance criterion | Text | The observable result the receiver agreed to inspect |
| Evidence reference | Text | Controlled record, section or run reference and its observation limits |
| Receiving reviewer | Text | Role or person who reviews the evidence in your private copy |
| Outgoing owner | Text | Role responsible for supplying evidence or correcting the gap |
| Required gate | Select | Required or Optional, agreed before review |
| Outcome | Select | Pending, Accept or Hold |
| Exception and next action | Text | Missing condition, responsible owner, remedy and review deadline |
| Retained responsibility | Text | Who still owns the affected operating task while it remains open |
| Review date | Date | Actual review date, entered when the review occurs |
The Table view shows all checks. Required gates filters Required gate to Required. A view filter does not restrict access to underlying records. There is no readiness formula or weighted score: the receiving owner must make the bounded acceptance decision.